Inside NSSF’s 30-Year Bet on Kenya’s Rironi–Mau Highway

Kenya’s National Social Security Fund (NSSF) has received parliamentary backing for its investment in the 233-kilometre Rironi–Mau Summit highway, with the pension fund positioning the project as a long-term income-generating asset.

By Parliamentary Outlook·

Share this story
Inside NSSF’s 30-Year Bet on Kenya’s Rironi–Mau Highway

Kenya’s National Social Security Fund (NSSF) has received parliamentary backing for its investment in the 233-kilometre Rironi–Mau Summit highway, with the pension fund positioning the project as a long-term income-generating asset.

The endorsement followed an inspection of the 81-kilometre Rironi–Gilgil section, where construction is approximately 40% complete. The contractor expects the Rironi–Naivasha–Gilgil stretch to become usable by March 2027.

The highway, launched in November 2025 under a public-private partnership (PPP), is divided into three sections: Rironi–Naivasha–Gilgil (81km), Rironi–Mai Mahiu–Naivasha (58km) and Gilgil–Nakuru–Mau Summit (94km). The full corridor is targeted for completion by June 2027.

The financing structure comprises 25% equity and 75% debt, with NSSF contributing 40% of the equity. Under the 30-year concession, the Fund expects to receive 40% of toll collections, while China Road and Bridge Corporation (CRBC) receives the remaining 60%.

For NSSF, the investment represents a strategic shift towards infrastructure assets that generate long-term income beyond traditional investments such as government bonds. Toll revenues are expected to provide relatively predictable returns while supporting the Fund's ability to meet future pension obligations.

The question is whether the highway can deliver sufficient traffic volumes and toll revenue to justify the investment over its 30-year concession.

For the pension industry, the project also demonstrates how long-term retirement savings can be channelled into infrastructure development.